Concrete test tasks can be used to schedule one or more concrete tests on samples. Notifications can be sent throughout the work process via email, SMS (text message), or internal notification within the program. To use this feature, the network version must be installed and the GaeaSynergy 4 Network Data Manager service running. These notifications can only be setup in tasks. The following notifications can be sent to selected personnel during the process:

 

Concrete test required

Concrete test completed

 

The "Concrete test required" notification will be sent when a test is required according to the Pour Date and the required Test Ages. The "Concrete test completed" notification will be sent when the test has been completed.

 

The status for the task will initially be "In Progress", then on the day when a concrete test is required it will change to "Concrete Test Required". When all the required concrete tests are complete the status will change to "Concrete Test Completed".

 

If the task type is Concrete Tests the Concrete Samples tab will be displayed.